Highland Drive Storm Sewer Replacement Project

**Posted to the City of Brecksville website January 8, 2024**

Project Description

  • This work consists of extending storm sewers primarily along the west side of the Highland Drive from 10270 Highland Drive to the Ohio Turnpike. The mainline sewer replacement is within the lawn area; however, there will be impacts to traffic due to staging of equipment and trucks. The contractor is required to maintain traffic during work hours and open both lanes each evening. The project does include two road crossings, and the contractor is to maintain traffic with road plates until the crossings are capped and suitable for traffic

  • City Council Awarded this project to the low bidder, Rising Son Company, LLC out of Ashland, Ohio in the amount of $153,828.00.


Anticipated Project Schedule

  • Start Date – On or around January 22, 2024

  • Substantial Completion Date – March 15, 2024 (excluding final asphalt, concrete, & restoration)

  • Completion Date - April 26, 2024 (weather dependent)